
THE ANDALUCIAN EXPEDITION ASSUMES THE
RESPONSIBILITY TO LEAD THE ASCENT TO
K2. UPDATE 12 + 1
ALMOST ALL
THE EXPEDITIONS ARE AT K2's Base camp
During
days we have been working hard to consolidate C2, each time we are more
certain that possibly the C1 - C2 trail is the most complicated of the ascent
to this mountain; not forgetting the last 650 meters of the climb. The work
of the last days is based on the fixation of new lines on the route and to
consolidate our camp two with the installation of a second tent and the
stocking of gas and food that will be consumed in the next days.
During the
work to equip the route, we have installed more than 1,500 meters of fixed
lines between advanced base camp and C2. Besides 140 meters installed by
three Czechs, all the job is under our responsibility. The following
expeditions are at the base of the mountain:
-
International: 3 climbers
-
Madrid: 3 climbers
-
Swiss: 10 climbers
-
Czech: 3 climbers
With the
presence of so many climbers at the base of K2, we hope to have more help in
the next days with the work on the route and we have more production than what
the Czech expedition is doing now... They have just installed a little more
than 100 meters of rope, and they have not opened a palm of trail, but they
should all be very strong because they have spent two nights at C2. To
valuate them better, let's not forget that they carried 300 meters of lines to
C1. That along with the Madrid expedition's and ours are the only ones that
hang rope from the sides of K2.
To do the
work so far, we have spent 22 days of BC, working with bad weather, although
we should better not complain and although we have not had more than three
days in a row of good weather, having 10 acceptable days is something good.
We need to mention our weatherman Javier Corripio, who is doing excellent
work and especially accurate.
The team
is doing fine and although we've had some problems, Fernando joined the works,
while Salazar continues with his fast but hard recovery, maybe next week we
will all be to our maximum again. Working with teammates who give themselves
as these do, and with an idea so clear and fixed like this one to reach the
summit of this difficult mountain, makes me happy and honors me. Andalucía
deserves more and more each time to be on the summit of K2.
All the
mountaineers who are at BC, because of the bad weather above, will dedicate
next week to improve our acclimatization and to prepare everything to install
C3. We are going to have a meeting of all the chiefs of expeditions in our BC,
to coordinate the works of installing lines up to C3. Manuel González
INTERESTING DATA
CAMPS
BASE CAMP
(BC) 4,950 METERS D: JUNE 5.
ADVANCED BASE
CAMP (ABC) 5,200 METERS T: JUNE 7
D: JUNE 8
CAMP 1 (C1)
5,950 METERS T: JUNE 10
D : JUNE 11
CAMP 2 (C2)
6,600 METERS T : JUNE 17
D : JUNE 26
T : FIRST
DAY THAT THE MARK WAS REACHED D: FIRST DAY WHEN CLIMBERS SLEPT
WEATHER
CONDITIONS
- 10
days of good weather
- 8
days of bad weather
- 6
days of regular to bad weather
PAKISTANI
TEAM
LINK OFFICER:
Amir (24 years old)
SIRDAR:
Ibrahim Akhon (46)
COOK: Ali
Rizia (35)
PINCHE: Ali
Mosa (18)
HIGH ALTITUDE
CARRIER: Golam Heder (36)
HIGH ALTITUDE
CARRIER: Ahmat (36)
ONE DAY IN
THE ASCENT OF K2: We are at C1 to finish the works of equipping the lines up
to C2, it will be my third day of climbing in this sector of the mountain and
although I already know the route, I am invaded by fears and doubts. We are
five climbers and we will divide the work in two: one group for the inferior
zone and the second up to C2.
At 12
hours an alarm clock rings and we begin the preparations, the night has no
moon and it is cold, we hardly talk and the triggers of our blocking fists are
opened as soon as possible, to begin the ascent through the first sections
with new lines, which we fixed a few days before, until the snow sent us down
to BC. The darkness gives a new character to the ascent: nobody talks, each
of us deep within our thoughts. Focusing on our work, opening the trail,
carrying ropes. Don't stop... it is cold. The waning mood appears on our
backs, trying to accompany us, the light is still only the white one coming
from our headlamps. Around 4 in the morning it starts to get clear, with the
light of dawn the good rope ends. The headlamps go off. The stops begin. I
remember my little daughter Alba. The sun begins to makes us happy... Juanjo
goes with us up to the bottom of House Chimney, Morales and I continue, fears
to try this vertical part with old lines and after Fernando's accident; the 20
meter ladder installed by Salarzar, and which we have Christianized by the
name of Saint Peter, is great help. I am above, good!
I fix the new line, I fix the header again and I yell to
Morales to climb. After sometime we are in C2. There is a little wind but
the day is good. We are in K2. One hour and a half
later we are in C1. During the descent we meet the Czechs who are climbing to
spend the night in C2. They are really strong. We have spent 11 hours to make
the pass safe, they would need only 3 hours to reach C2. I think those are
different ways to climb K2. LOLO Translated from Spanish to Jorge Rivera
Dispatches
Pictures and text copyright
ANDALUCIA K2 expedition
 |
Altitech2:
Digital Altimeter, Barometer, Compass and Thermometer. Time/Date/Alarms.
Chronograph with 24 hour working range. Timer with stop, repeat and up
function. Rotating Bezel. Leveling bubble. Carabiner latch. E.L. 3 second
backlight. Water resistant. 4" x 2-1/4" x 3/4" 2 oz. Requires 1 CR2032
battery.
See more here. |
|

|
|